Azizi Central construction is 57% complete

Azizi Central offers a range of one-, two-, and three-bedroom apartments designed to cater to modern lifestyle requirements

Azizi Developments has announced that the construction of Azizi Central, its contemporary residential development within Dubai’s Al Furjan community, has reached a milestone of 57% completion. The handover of this development is scheduled for Q4 of this year.

Strategically located in one of Dubai’s fastest-growing residential areas, Azizi Central offers a range of one-, two-, and three-bedroom apartments designed to cater to modern lifestyle requirements. The developer says that the development features curated exteriors and interiors, blending comfort and sophistication.

Azizi Central will boast an array of amenities that cater to the diverse needs of its residents. These include landscaped walk-in areas, gym, separate pools for adults and children, an outdoor seating area, a BBQ zone, and ample parking facilities. Additionally, the development offers a variety of retail and dining options, ensuring that residents have access to everyday essentials and leisure activities, the developer confirmed.

Azizi said that the structure of the development is fully completed, and the blockwork and internal plastering have reached 97% and 95% completion respectively. Tiling has also been completed to 18%, while HVAC and MEP installations are progressing at 64% and 53%.

Group CEO Farhad Azizi said, “We are thrilled with the steady momentum at Azizi Central, our development in the high-growth corridor of Al Furjan. As part of our commitment to timely delivery and exceptional build quality, every phase of construction is being closely supervised to ensure it meets the highest standards. Azizi Central is thoughtfully designed to offer a truly elevated lifestyle, combining modern comfort, everyday convenience, and connectivity. We look forward to welcoming our valued homeowners to their new residences by the end of the year,”

The developer also shared the completion of certain façade works, elevator installation, and overall finishes. Façade works have reached 50% completion, elevator installation stands at 22% completion, and overall finishes are at 37%. To expedite project work, Azizi says it has deployed a total of 414 workers.