Iraq’s Ministry of Electricity and GE Vernova delivers five substations
Upon completion of the 10 substations, the Iraqi transmission system will be able to transmit an additional 2,200MVA of power
The Ministry of Electricity (MoE) and GE Vernova have announced the early completion and energisation of five critical substations across the country in less than two years. These substations are said to be part of a nationwide project that involves the energisation of 10 substations by Iraq’s MoE and GE Vernova to improve grid stability, network efficiency and enable the interconnection with the Hashemite Kingdom of Jordan’s grid, providing more stable electricity for the people of Iraq.
The five new 132kV substations include Al Hindia, Al Sader, Al Qaim Saada, North Baqubah and Yaramja South. Both the North Baqubah and Yaramja South substations were delivered around six months ahead of schedule and were completed in August and September 2024. Construction and equipment installation works at the Rasafa Center substation have reached the final stages and will be energised soon, said a statement.
Four additional substations, North Najaf, North Karbala, North Diwaniya and Aredo, are scheduled for completion by summer of 2025.
Upon completion of the 10 substations, the Iraqi transmission system will be able to transmit an additional 2,200MVA of power, enabling improved transmission of the equivalent amount of electricity needed to power approximately 300,000 households or about one million people, it added.
“The strategic collaboration with reputable international companies, such as GE Vernova, supports the Ministry’s efforts to modernise the national electricity grid by enhancing generation and transmission efficiency, and providing a reliable technical map that provides flexibility in transferring loads and achieving stability in connecting to each other,” said Iraq’s Minister of Electricity, Ziad Ali Fadhil.
He added, ”In this context, these five substations that were completed and energised ahead of schedule represent a key milestone and an important addition to our efforts as they directly contribute to improving the stability of the grid in the surrounding areas, and are necessary to meet the growing demand for electricity. The completion of these complex projects ahead of schedule demonstrates the commitment of the Ministry of Electricity teams and their focus on achieving tangible results.”
Johan Bindele, Leader of GE Vernova’s Grid Systems Integration business added, “By executing these transformative electrification projects in partnership with the Ministry, our advanced substation solutions are not only stabilising the grid but also accelerating Iraq’s transition to a more reliable, affordable, and sustainable energy future.”
Rasheed Janabi, President of GE Vernova in Iraq noted, “As a dedicated, long-term player in the energy sector in Iraq, we are committed to meeting the growing energy needs of Iraq’s economy with the latest technologies and solutions across the energy value chain. This latest grid modernisation milestone is part of a comprehensive strategy that GE Vernova developed to help accelerate Iraq’s transition to more reliable and lower carbon power for the benefit of present and future generations. We are proud of the key role of the Iraqi team members from both GE Vernova and MoE in these projects.”
Over the past decade, GE Vernova has built and energised a total of 30 substations, including five 400kV substations in Al Khairat, Nainawa, Mansouriya, Mosul East, Al Fao and Baghdad Northwest. In addition, four132 kV substations were completed in Dohuk province in Kurdistan region, further strengthening Iraq’s power infrastructure.