Azizi Developments: 92% of construction has been completed on Farishta tower in Al Furjan

Azizi Developments, a UAE-based private developer, has announced that nearly 92% of construction has been completed on its Farishta tower in the Al Furjan area of Dubai.

Comprising of 284 residences with a mix of 137 studios, 123 one-bedroom and 15 two-bedroom apartments, along with eight penthouses, the project is on schedule for delivery and is expected to be handed over in the fourth quarter of 2019, the developer said in a statement.

External works are now more than 70% complete, it added. 100% of the structure and 99% of the blockwork have been completed, while tiling and heating, ventilation and air-conditioning (HVAC) works are at 99% and 92% respectively.

The second fix of MEP works is at 95%, while façade works are at 92%, the statement said. Overall finishing stands at 89%.

Farishta is part of more than 20 projects lined up by Azizi Developments in the Al Furjan area. It is situated in the high-growth corridor of new Dubai, in a location that has easy access to the Expo 2020 Dubai site, Ibn Battuta Mall, Dubai Marina and JBR, amongst other points of interest in Dubai.

“It fills us with pride to know that we will soon be delivering another remarkable project in Al Furjan, a promising area that is very dear to us. With the strong customer response that this development has received, delivering the 284 units on time remains a top priority to us,” said Farhad Azizi, CEO of Azizi Developments.